2022 Capital Improvement Projects

Street Reconstruction Projects

  • Queens Street - Ring Street - Dover Way - Harvard Drive - Major Way
  • Barbara Street
  • Dewey Street - Chase Boulevard - Blankenheim Lane
  • Amanda Avenue

Street Rehabilitation Projects

  • Joshua Circle
  • North Bristol (from Windsor Street to Klubertanz Drive)

Water Main Project 

  • Grove Street

Street Extension Project

  • Columbus Street


2022 Construction Updates

Pheasant Run Street Reconstruction (Queens St., Ring St., Dover Way, Harvard Dr., Major Way) & Joshua Circle Pavement Rehabilitation:

6/13 Update: The contractor will continue with tree removals 6/13 through 6/14. They will mobilize for the sanitary sewer replacement on Ring Street and Queens Street on 6/13 and begin working on the sanitary sewer on 6/14 just west of Covey Street. The sanitary replacement may take 2 weeks to complete. On Wednesday 6/15, another underground crew will start on storm sewer at Sunfield and Dover and will continue with that for the remainder of the week. The contractor will start curb and gutter spot replacements next week on Joshua Circle. 

The project is scheduled to be completed by September 1. 

Barbara Street Reconstruction & Jeanne Court Pavement Rehabilitation:

6/20 Update: The concrete contractor will be in setting line tomorrow and placing curb and gutter on Thursday. They may start forming for sidewalk Friday or early next week. Residents will not have access to their driveways until the sidewalk and driveway aprons have been placed and cured (approximately 5-7 days).

This is project is scheduled to be completed by July 26.

Dewey Street - Chase Boulevard - Blankenheim Lane Street Reconstruction:

6/20 Update: The contractor indicated that construction will begin on July 5. The contractor will have 60 calendar days to complete the work.