2021 Capital Improvement Projects

Street Reconstruction Projects

  • Chickory Way - Aspen Place - Juniper Street
  • Wyoming Avenue 
  • Cliff Street
  • Barr Street 
  • Miller Street - Trapp Street

Concrete Pavement Project 

  • North Bird Street

Street Rehabilitation Projects

  • North Bristol Street 
  • Sapphire Way: Clarmar Drive to Castle Drive
  • Castle Drive 
  • Fountain Drive 
  • Rustic Drive: Clarmar to Fountain 
  • Oconto Drive: Clarmar to Fountain 
  • Fireside Court 
  • Villa Circle 
  • Walker Court 

Pedestrian Improvement Projects 

  • West Main Street

CHICKORY WAY – ASPEN PLACE - JUNIPER STREET RECONSTRUCTION PROJECT

This project is scheduled to begin with tree removals and asphalt pulverization beginning the week of April 26th. The asphalt pavement on the streets will be pulverized and will be used as a working surface during construction. The underground utility work will begin mid-week and will continue until early June. The project will include new curb & gutter, asphalt pavement, sidewalks on both sides of the streets, new water main and services, sanitary sewer repairs and storm sewer repairs and extensions. The project is anticipated to be completed by early August.

WYOMING AVENUE RECONSTUCTION PROJECT

This project is scheduled to begin the week of June 28th on Wyoming Avenue with tree removal and asphalt pulverization. The asphalt will be pulverized, graded, rolled and used as a working surface during construction. The underground work will begin mid-week and will continue for approximately 2-3 weeks. The project will include new curb & gutter, asphalt pavement, storm sewer extensions and adding sidewalks to both sides of Wyoming Avenue. The project is expected to be completed early September. 

CLIFF STREET RECONSTUCTION PROJECT

This project will consist of new water main and services, sanitary sewer repairs, new curb & gutter, sidewalks, and asphalt pavement. The project is scheduled to begin June 28th with pulverizing the asphalt and tree removals. The underground utility work should take approximately 2 weeks. The project is anticipated to be completed by August 9th. 

BARR STREET RECONSTRUCTION PROJECT

This project is scheduled to begin mid-July with pavement and concrete removals. The project will include new curb & gutter on the south side and new asphalt pavement. The project is scheduled to be completed by early August.

MILLER STREET – TRAPP STREET RECONSTRUCTION PROJECT

This project is scheduled to commence the week of May 26th with tree removals and asphalt pulverization. The project will include new water main and services, storm sewer extensions, new curb & gutter, sidewalks on both sides of the streets and new asphalt pavement. Underground utility work will begin mid-week after pulverization and will continue for approximately 4 weeks. The project is anticipated to be completed by mid-August.

NORTH BIRD STREET CONCRETE PAVEMENT PROJECT 

This project will consist of spot repairs to curb & gutter, sidewalks and providing a curb bump-out at Frederick Street to provide a safer pedestrian crossing. The project will also consist of removing the asphalt pavement and replacing it with concrete pavement. The project will occur between May and September, however the contractor will have 40 calendar days to complete the project once they begin.

NORTH BRISTOL STREET PAVEMENT REHABILITATION PROJECT

 The scope of this project will be on N Bristol Street from Tower Drive to Progress Way. The project will include storm sewer extensions, new asphalt pavement, curb & gutter on the east side north of Business Park Drive and bike paths to Progress Way. The project is scheduled to take place between May 15th and September 15th however the contractor will have 75 calendar days to complete once they begin. 

2021 PAVEMENT REHABILITATION PROJECT 

The following streets will have curb & gutter spot repairs and new asphalt pavement installed as part of this project: 

 Sapphire Way: Clarmar Drive to Castle Drive

 Castle Drive

 Fountain Drive

 Rustic Drive: Clarmar to Fountain

 Oconto Drive: Clarmar to Fountain 

 Fireside Court

 Villa Circle 

 Walker Court 

This project will also include storm sewer improvements along Castle Drive to Sunny Valley Park. 

The project is scheduled to occur between May 15th and September 15th however it shall be limited to 60 calendar days once the project begins.

WEST MAIN STREET PEDESTRIAN IMPROVEMENTS 

This project will include installing a pedestrian crossing in West Main Street near the Park Circle entrance just west of the Hart Road and Clarmar Drive intersection that features Rectangular Rapid Flash Beacons (RRFB). The pedestrian crossing will also feature a pedestrian refuge median in W Main Street to enhance safety for pedestrians crossing W Main Street. 

The RRFB’s will be push button activated by the pedestrian’s crossing W Main Street to improve pedestrian safety by alerting oncoming traffic of the presence of pedestrians in the crosswalk. 

The project is scheduled to be completed by September.