2021 Capital Improvement Projects

Street Reconstruction Projects

  • Chickory Way - Aspen Place - Juniper Street
  • Wyoming Avenue 
  • Cliff Street
  • Barr Street 
  • Miller Street - Trapp Street

Concrete Pavement Project 

  • North Bird Street

Street Rehabilitation Projects

  • North Bristol Street 
  • Sapphire Way: Clarmar Drive to Castle Drive
  • Castle Drive 
  • Fountain Drive 
  • Rustic Drive: Clarmar to Fountain 
  • Oconto Drive: Clarmar to Fountain 
  • Fireside Court 
  • Villa Circle 
  • Walker Court 

Pedestrian Improvement Projects 

  • West Main Street

Project Updates

CHICKORY WAY – ASPEN PLACE - JUNIPER STREET RECONSTRUCTION PROJECT

July 26, 2021 Update: Contractor will begin paving the remaining asphalt driveways on July 31. Neighborhood residents are asked to move all vehicles out of their driveways and park a house away this day so the work can be completed on time. 

The contractor is scheduled to pave the final layer of asphalt on the streets on August 2. Neighborhood residents are asked to move vehicles out of the streets during this time. 

This project is anticipated to be completed by early August. 

WYOMING AVENUE RECONSTUCTION PROJECT

August 23, 2021 Update: The contractor will finish concrete work early this week. They will finish grade Tuesday and Wednesday and pave the first layer of asphalt on Thursday, weather permitting. The restoration crews will follow up placing topsoil, seed, fertilizer, and mulch. The tentative plan is to have the final layer of asphalt placed on September 8. 

CLIFF STREET RECONSTUCTION PROJECT

This project will consist of new water main and services, sanitary sewer repairs, new curb & gutter, sidewalks, and asphalt pavement. The project is scheduled to begin June 28th with pulverizing the asphalt and tree removals. The underground utility work should take approximately 2 weeks. The project is anticipated to be completed by August 9th. 

BARR STREET RECONSTRUCTION PROJECT

This project is scheduled to begin mid-July with pavement and concrete removals. The project will include new curb & gutter on the south side and new asphalt pavement. The project is scheduled to be completed by early August.

MILLER STREET – TRAPP STREET RECONSTRUCTION PROJECT

August 5, 2021 Update: The contractor plans to begin asphalt paving early next week and will pave both the binder course and surface course. The paving operations could take two days to complete. The longer residents stay off the pavement after paving operations are complete the better-- a few hours will allow the pavement to cool and prevent marring of the pavement from turning vehicles. 

The project is anticipated to be completed by mid-August.

NORTH BIRD STREET CONCRETE PAVEMENT PROJECT 

August 30, 2021 Update: The contractor plans to pour the east half (northbound) of N Bird Street Tuesday and Wednesday. The curing time is typically 5 to 7 days until it is open to traffic. The contractor will have some curb and gutter, asphalt pavement at the side streets and pavement markings to install week prior to opening the street to through traffic. 

NORTH BRISTOL STREET PAVEMENT REHABILITATION PROJECT

August 12, 2021 Update: The contractor plans to finish grading the multiuse path and road this week. They are scheduled to start pouring the concrete curb and gutter next week. The contractor will notify residents/businesses if/when their driveways will be impacted. 

Temporary detour: Willburn - Corporate Center - Progress

This project is scheduled to take place between May 15 and September 15, however the contractor will have 75 calendar days to complete it once they begin. 

2021 PAVEMENT REHABILITATION PROJECT 

The following streets will have curb & gutter spot repairs and new asphalt pavement installed as part of this project: 

  • Sapphire Way: Clarmar Drive to Castle Drive
  • Castle Drive
  • Fountain Drive
  • Rustic Drive: Clarmar to Fountain
  • Oconto Drive: Clarmar to Fountain 
  • Fireside Court
  • Villa Circle 
  • Walker Court 

This project will also include storm sewer improvements along Castle Drive to Sunny Valley Park. 

The project is scheduled to occur between May 15th and September 15th however it shall be limited to 60 calendar days once the project begins.

WEST MAIN STREET PEDESTRIAN IMPROVEMENTS 

This project will include installing a pedestrian crossing in West Main Street near the Park Circle entrance just west of the Hart Road and Clarmar Drive intersection that features Rectangular Rapid Flash Beacons (RRFB). The pedestrian crossing will also feature a pedestrian refuge median in W Main Street to enhance safety for pedestrians crossing W Main Street. 

The RRFB’s will be push button activated by the pedestrian’s crossing W Main Street to improve pedestrian safety by alerting oncoming traffic of the presence of pedestrians in the crosswalk. 

The project is scheduled to be completed by September.